The Environmental Case Law Index is a collection of judgments from 10 African countries on topics relating to environmental law, both substantive and procedural. The collection focuses on cases where an environmental interest interacts with governmental or private interests.
Get started on finding judgments that are relevant to you by browsing the topic list on the left of the screen. Click the arrows next to the topic names to reveal a detailed list of sub-topics. Most judgments are accompanied by a short summary written by subject-area expert postgraduate students from the University of Cape Town.
Read also JIFA's Environmental Country Reports for SADC
This was an appeal from a decision in an application for judicial review. The appellant was aggrieved by the lower court’s finding that the appellant was not entitled to the orders sought for failure to disclose that an appellate procedure existed under s 129 of the Environmental and Management Co-ordination Act 1999 (EMCA) and not demonstrating why judicial review was preferred to an appeal to the National Environmental Tribunal under the act, upon being dissatisfied with the National Environmental Management Authority’s (NEMA) decisions.
NEMA had ordered the appellant to conduct a fresh Environmental Impact Assessment (EIA) under s 138 of the EMCA and to cease construction on the suit land.
The court determined whether the trial judge erred in finding that the appellant failed to demonstrate that judicial review was more suitable than an appeal to the tribunal.
The court held that the trial judge arrived at the right conclusion. The court applied the rule that, where an alternative remedy such as a statutory appeal procedure existed, judicial review can only be granted in exceptional circumstances. The court noted that the appellant failed to demonstrate these exceptional circumstances and should have made an appeal to the tribunal instead.
The court also found that public participation is a crucial aspect in environmental matters. The court noted that the fresh EIA as ordered by NEMA would give the appellant an opportunity to ensure public participation which had been ignored in the first EIA.
Accordingly, the appeal was dismissed.
This was an application for review of the respondent’s decision to authorise the construction of a lodge in a protected area. The lodge was built prior to obtaining the necessary environmental authorisation but this was obtained ex post facto. The applicant had at the time of filing this application alos filed an application for an interdict to stop the construction of the lodge, which application was dismissed.
The main legal issue to be resolved was whether under the National Environmental Management Act No 107 of 1998 (NEMA) a permit to build a house in the Protected Environment (MPE) could be issued ex post facto as was given to the third respondent by the first and second respondents.
The court held that section 24 G of NEMA provided for the rectification of the unlawful commencement of the activity by applying to the Minister or MEC for an ex post facto environmental authorisation. In conclusion, the court held that since the application was done and approved ex post facto the respondents had acted within the confines of the law and therefore the application lacked merit. The court observed further that the was aware, or ought to have been aware that when it was unsuccessful in the urgent application to have the development of the Lodge suspended, the consequences were that the respondent would continue with the construction and finalisation of its building project and the review would be rendered academic. Accordingly, the application was dismissed.
The first plaintiff concluded a tribute agreement with the second and third defendants that was to last for ten years. The Mining Commissioner rejected this agreement since it was not registrable. This agreement was replaced by a three-year tribute agreement. When this agreement expired, the first plaintiff entered into another agreement with the second plaintiff and they sought an order registering this agreement and the eviction of the second and third defendant. The eviction order was opposed on grounds that the first agreement was still valid.
In interpreting s289 and 290 of the Mines and Minerals Act on tribute agreements, the court made a distinction between directory and peremptory provisions. The court noted that it is impossible to lay down any conclusive test to distinguish the two provisions. However, provisions in negative form and containing penal sanctions are to be regarded as peremptory rather than directory. The court also noted that the intention of the legislature is to be considered when distinguishing the two.
The court found that the provisions were couched in negative form and that their contravention was to be visited with penal sanctions, hence peremptory. Additionally, it was found that the approval was meant to protect the interests of the tributor and to avoid premature cessation of mining operations.
Accordingly, the court declared that the first agreement was invalid and unenforceable; and that the second agreement was valid but had expired. Consequently, the second and third defendants were ordered to vacate or be evicted.
This matter dealt with a dispute as to whether there was illegal mining by the respondent on the applicant’s exclusive prospecting licence.
The High Court considered whether expert evidence was required to establish a cause of action. The relevant test was whether a witness proffering an opinion is competent to give one on the matter in dispute. In this case, the court considered that only a land surveyor would be competent to determine the precise boundaries of disputed land. The applicant’s witness was a geologist and not a land surveyor. Accordingly, the court held that expert evidence of a land surveyor was necessary and failure to present it was fatal.
The court also considered whether it was permissible for the applicant to introduce new evidence in the replying papers. The court relied on the principle that in motion proceedings the affidavits constitute both the pleadings and the evidence. Furthermore, the applicant could not substitute a different claim in the replying papers. Accordingly, the court did not consider the evidence of the land surveyor tendered by the applicant during motion proceedings.
Finally, the court considered whether to impose a special costs order against the applicant on the scale as between attorney and own client. The principle followed was that punitive costs should only be awarded in exceptional circumstances. The court considered that there was no demonstrable reprehensible conduct by the applicant. Accordingly, the costs only include the costs of one instructing and one instructed counsel.
The applicant sought to review and set aside the decision of the Central Farm Dwellers Tribunal (“tribunal”), to evict the applicant.
The decision handed down by the first respondent was initially taken on appeal to the tribunal, which originally denied the request for an appeal as it was filed out of time. The matter was then referred to the Supreme Court, which referred the matter back to the tribunal.
The applicant argued that the decision of the first respondent was reviewable because of the first respondent’s failure to decide whether it acquired the land on which it was situated through acquisitive prescription.
The court considered whether or not it was irregular for the first respondent to direct that the second and third respondents could evict the applicant when there was a claim by the applicant that had not been determined, i.e. the acquisition of the land. The court held that to authorize an eviction before determining the acquisitive prescription would not accord to anyone’s sense of justice.
The court found that the irregular step of the first respondent in authorizing the applicant’s eviction was sufficient to warrant a review and that the court would have to substitute the decision of the first respondent with that of its own.
Application upheld.
The applicants in this matter approached the high court seeking, inter alia, an interdict preventing the respondents from evicting 140 school children and from demolishing their homesteads.
The residents occupied the land in question through the traditional system of Khonta. After paying the prescribed livestock and fees to the area’s chief, they were allowed to settle on the land. However, it was later discovered that the land belonged to the Swaziland National Provident Fund and was therefore not under the control of the chief.
The applicants argued that the evictions were arbitrary and contravened s 18 and 29 of the Swaziland Constitution and that such evictions were a threat to education of their children.
The court first dealt with the issue of urgency and concluded that the court was prepared to hear the matter on an urgent basis. The court in deciding the matter weighed the rights of the children against those of property owners as contained in the Constitution. It concluded that the rights of children did not supersede the rights of the property owners. Therefore, the court held that the applicants failed to establish the requirements of an interdict and the rest of the orders they were seeking.
The matter was dismissed with costs.