Get started on finding judgments that are relevant to you by browsing the topic list on the left of the screen. Click the arrows next to the topic names to reveal a detailed list of sub-topics. Most judgments are accompanied by a short summary written by subject-area expert postgraduate students from the University of Cape Town.
Read also JIFA's Environmental Country Reports for SADC
The matter dealt with an alleged breach of contract that required the plaintiff to supply large amounts of water to the defendantís wine farm. The contract contained two main clauses namely, that the defendant would reimburse the plaintiff a maximum of N$300000 for obtaining tenders and would design and construct the bulk water supply scheme in the absence of an alternative agreement.
The plaintiff contended that the agreement was never entered into despite the work being carried out and as a result, they were entitled to reimbursement because the defendant breached the two main clauses of the contract. In response, the defendant alleged that the plaintiff was vicariously guilty of breach of contract as a result of which the defendant says it terminated contract.
The main question before the court was whether the plaintiff was vicariously guilty of breach of contract which resulted in the defendantís termination of the contract and in the alternative. The court also considered whether the respondent would be required to pay for the work done as per the agreement.
The court found that no such breach existed and that had there been a breach, the defendant, would have been required to communicate termination of the contract which it failed to do. The court concluded that the reliance on an alleged oral agreement had not been proved by facts ëíin the clearest and most satisfactory manneríí. The court found in favour of the applicant.
The plaintiff in this case claimed restitution for a breach of contract. The court determined whether the defendant was in breach of contract for failing to install a working borehole in a geohydrological environment where the plaintiff's farm was located.
The defendant raised a counterclaim that the plaintiff had accepted that work was completed but failed to pay the balance of the agreed amount. The court applied the rule in Du Plessis v Ndjavera that the plaintiff is under no obligation to perform before defendant has completed his performance.
The court held that the defendant was at fault for failing to assess the soil formation in the area and ended up using the incorrect drilling method. The court observed that the defendant admitted to using the riskier direct flush air percussion instead of the mud rotary method to save on expenses and thus failed to complete performance.
Accordingly, the court held that the defendant was in breach of contract and the plaintiff was entitled to cancel the
agreement and claim restitution. The counterclaim was also dismissed with costs.